Byculla flyover 30% built and likely to miss its May 2028 deadline
The cable-stayed bridge meant to ease congestion around J.J. is expected to run five to six months late
My Maha Rashtra News Desk, Mumbai City
Published:

Mumbai: Work on the Byculla flyover, which the Brihanmumbai Municipal Corporation is building to ease traffic congestion around J.J. in Byculla, has not picked up the expected pace. About 30% of the bridge is reported to be complete, and because the construction is technically demanding, its May 2028 completion deadline is expected to slip by five to six months.
The flyover will connect the Sitaram Silam flyover (Y bridge) in Byculla with the J.J. flyover, and work is under way at the junction of J.J. Marg and the Sabu Siddique Polytechnic. Its main cable-stayed section will be about 230 metres long and its viaduct 312 metres, with two lanes in each direction. It is being built of reinforced concrete and structural stainless steel.
The civic body's additional commissioner Abhijit Bangar recently inspected the project and ordered the work speeded up, but the nature of the construction makes the deadline hard to meet, according to the report.
Once complete, the bridge is expected to ease congestion at junctions on Sir J.J. Road and in Byculla, Nagpada and Mazgaon, one of South Mumbai's busiest traffic belts, cutting travel time and fuel use.
Source: Pudhari
Stay with My Maha Rashtra
Related stories
- Tiger Shroff firing case: four detained, including two women; Mumbai Police get three-day transit remand
- Diwali 2026 in Maharashtra: Vasubaras on 5 November, Lakshmi Pujan on the 8th and Bhaubeej on the 11th; the full calendar and muhurat
- Drought at the centre of the Dasara rallies: Uddhav Thackeray at Shivaji Park, Eknath Shinde at NESCO; who said what
- India-New Zealand T20 series from Thursday: Mumbai’s Shreyas Iyer leads; the five-match schedule and full squad
- Dasara weather: clear skies and 36°C in Mumbai; showers likely in Kolhapur and Sindhudurg
- Banks and the share market are shut today for Dasara; UPI and ATMs work as usual, and business resumes on Wednesday
https://mymaharashtra.in/en/maharashtra/byculla-flyover-likely-to-miss-may-2028-deadline-10266